5.4 Measurement process for reinforcement using CostX software
When calculating the total length of reinforcement bars, it is important to account for the concrete cover (cc) as shown in Figure 5.5. In addition, you must allow for the inclusion of hooks or cogs (refer to Figure 5.6) where applicable. If the details of hooks or cogs are not clearly specified on the structural drawings or in the project specifications, then the minimum requirements set out in relevant Australian Standards, such as AS3600 (Concrete Structures), should be used during the measurement process.


The following steps are typically followed to determine the quantity of reinforcement bars required for a construction project:
Step 1: Calculate the total length of reinforcement bars
- Determine the total length by multiplying the number of bars by the length of each bar.
- Total length of bars (m) = Number of bars × Length of each bar
Step 2: Obtain the unit weight of the bar
- Refer to Table 5.1 below to find the mass per unit length (in kg/m) for the specific diameter of the reinforcement bar being used. These values are based on standard steel bar sizes. Alternatively, you can calculate the weight per meter using the formula:
- Unit weight (kg/m) = (Diameter in mm) ² ÷ 162
Step 3: Calculate the total weight in kilograms
- Multiply the total length of the bars (from Step 1) by the unit weight (from Step 2).
- Weight (kg) = Total length of bars (m) × Unit weight (kg/m)
Step 4: Convert the weight from kilograms to tonnes
- Finally, convert the total weight from kilograms to tonnes by dividing the weight in kg (Step 3) by 1,000.
- Weight (tonnes) = Weight (kg) ÷ 1,000
| Nominal Diameter (mm) | Mass per meter linear (kg/m) | Nominal Diameter (mm) | Mass per meter linear (kg/m) |
| 6 | 0.222 | 20 | 2.469 |
| 8 | 0.395 | 24 | 3.556 |
| 10 | 0.617 | 28 | 4.840 |
| 12 | 0.889 | 32 | 6.321 |
| 14 | 1.210 | 36 | 8.000 |
| 16 | 1.580 | 40 | 9.887 |
5.4.1 Computer-based measurement of reinforcement for pad footings
Based on the drawings provided below (Figures 5.7 to 5.9), perform a digital quantity take-off for the reinforcement bars in the pad footings. Using the measured quantities, prepare a detailed BQ using iTWO CostX software.



The following steps show how to measure pad footing reinforcement bars:
Step 1: Add the drawings and calibrate X and Y axis (Figures 5.10 and 5.11).


The calibration can be checked by remeasuring the distance between two known points on the calibrated drawing as follows (Figure 5.12).

Step 2: Add dimension groups (Figures 5.13 to 5.16).
- Dimension group for X-bars for PF1
“Default Multiplier” = 6 pad footings (PF1) × 1 layer of reinforcement (bottom layers of reinforcement for each footing) = 6

- Dimension group for Y-bars for PF1
“Default Multiplier” = 6 pad footings (PF1) × 1 layer of reinforcement (bottom layers of reinforcement for each footing) = 6

- Dimension group for X-bars for PF2
“Default Multiplier” = 6 pad footings (PF2) × 2 layer of reinforcement (top and bottom layers of reinforcement for each footing) = 12

- Dimension group for Y-bars for PF2
“Default Multiplier” = 6 pad footings (PF2) × 2 layer of reinforcement (top and bottom layers of reinforcement for each footing) = 12

Step 3: Measure bars (Figures 5.17 to 5.20).
- Measure X-bars for PF1 (Figures 5.17 and 5.18)
To measure reinforcement bars, first activate the “Rebar” tool. Set the bar spacing to 200 mm (0.2 m), as specified in the Pad Footing Schedule on the drawing. For example, ‘PF1 N16-200 Bottom’ indicates that 16 mm diameter bars are placed at 200 mm centres at the bottom of the pad footing. Next, account for the additional bar length required for cogs (bends) at each end. Each bar includes two 350 mm bends, totalling 700 mm (0.7 m). This extra length can be measured from Section 1-1 of the drawing (Figure 5.17) and should be checked against the minimum requirements in the Australian Standard (AS3600).
Alternatively, the cog length can be calculated by deducting the concrete cover from the overall depth of the footing. In this case, the depth of the pad footing is 450 mm, and the concrete cover is 50 mm at both the top and bottom. Subtracting these values gives a cog length of 350 mm (i.e. 450 mm – 50 mm – 50 mm). According to AS3600-2009, the minimum required cog length for a 16 mm diameter bar is 220 mm, so the calculated 350 mm length meets the standard.


- Measure Y-bars for PF1 (Figure 5.19)


- Measure X-bars for PF2 (Figures 5.21 and 5.22)
The additional bar length required for cogs (bends) at each end includes two 350 mm bends, totalling 700 mm (0.7 m). This extra length can be measured from Section 2-2 of the drawing and should be checked against the minimum requirements in the Australian Standard (AS3600).
Alternatively, the cog length can be calculated by deducting the concrete cover from the overall depth of the footing. In this case, the depth of the pad footing is 450 mm, and the concrete cover is 50 mm at both the top and bottom. Subtracting these values gives a cog length of 350 mm (i.e. 450 mm – 50 mm – 50 mm). According to AS3600-2009, the minimum required cog length for a 20 mm diameter bar is 260 mm, so the calculated 350 mm length meets the standard.


- Measure Y-bars for PF2 (Figure 5.23 and 5.24)


Step 4: Add workbooks, transfer quantities and write descriptions (Figures 5.25 to 5.28).


Write preamble notes and items, as well as the description of reinforcement on the second level.

- The weight per metre of a 20 mm reinforcement bar is 2.469 kg/m, and for a 16 mm bar, it is 1.58 kg/m (refer to Table 5.1).
- Convert the weight to tonnes using the conversion factor: 1 tonne = 1,000 kg.

Step 5: Generate reports (Figures 5.29 to 5.31)
- Choose the report format (e.g. “Bill of Quantities – 2 Levels”) and generate the report.

- Edit report details such as report title and create preview.


5.4.2 Computer-based measurement of reinforcement for beam
Based on the drawings provided below (Figures 5.32 and 5.33)–, perform a digital quantity take-off for the reinforcement in beams on axis 1. Using the measured quantities, prepare a detailed BQ using iTWO CostX software.


The following steps show how to measure beam reinforcement:
Step 1: Upload the drawings and calibrate them (Figures 5.34 to 5.35).


Step 2: Create dimension groups (Figure 5.36 to 5.38).
- Dimension group for top and bottom bars
The “Default Multiplier” is set to 4 because the reinforcement configuration includes two identical top bars and two identical bottom bars, resulting in a total of four identical bars being accounted for in the calculation.

- Create a dimension group for beam stirrups to measure one vertical side of the stirrup.

- Create a dimension group for beam stirrups to measure the top, bottom and vertical sides of the stirrup (extra distance).

Step 3: Measure and show markups (Figures 5.39 to 5.42).
- Measure the top and bottom bars of the beam.

- Measure stirrups for beam (extra distance part).

Note: The total extra bar length is calculated as follows:
- Measured extra distance in CostX = 0.76 m
- Hook length (from standard- AS3600) for 6 mm diameter bar = 150 mm (or 0.15 m) per hook
- Total extra distance = 0.76 m + 2 × 0.15 m = 1.06 m (or 1,060 mm).

- Markup for the entire beam on axis 1.

Step 4: Create workbooks and transfer quantities (Figures 5.43 to 5.45).
- Transfer quantities for the beam main bars.

- Transfer quantities for the beam stirrups.


Step 5: Generate reports (Figure 5.46).

5.4.3 Computer-based measurement of reinforcement for column
Based on the drawings provided below (Figure 5.47 to 5.49), perform a digital quantity take-off for the reinforcement in columns (C1 and C2) on axis 1. Using the measured quantities, prepare a detailed BQ using iTWO CostX software.



The following steps show how to measure column reinforcement:
Step 1: Upload the drawings and calibrate them (Figure 5.50).

Step 2: Create dimension groups (Figures 5.51 and 5.52).
- Dimension group for main bars – C1
The “Default Multiplier” is set to 12 because the reinforcement configuration consists of six identical vertical bars in each of the two C1 columns, resulting in a total of twelve identical bars considered in the calculation.

- Dimension group for main bars – C2
The “Default Multiplier” is set to 12 because the reinforcement configuration consists of six identical vertical bars in each of the two C2 columns, resulting in a total of twelve identical bars considered in the calculation.

Step 3: Measure and show markups (Figure 5.53 to 5.63).
Measure the main reinforcement bars for Column C1 (Figures 5.53 to 5.58).
Note: Starter bars are to be measured separately and are not included in this quantity.

Measure ligatures for C1 (extra distance).


The total extra bar length is calculated as follows:
- Measured extra distance in CostX = 0.77 m
- Hook length (from standard) for 10 mm diameter bar = 180 mm (or 0.18 m) per hook
- Total extra distance = 0.77 m + 2 × 0.18 m = 1.13 m (or 1,130 mm).



Measure the main bars for C2 (Figures 5.59 to 5.63).
Note: Starter bars are to be measured separately and are not included in this quantity.

Measure ligatures for C2 (extra distance).


The total extra bar length is calculated as follows:
- Measured extra distance in CostX = 1.22 m
- Hook length (from standard) for 10 mm diameter bar = 180 mm (or 0.18 m) per hook
- Total extra distance = 1.22m + 2 × 0.18 m = 1.58 m (or 1,580 mm)


Step 4: Create workbooks and transfer quantities (Figures 5.64 to 5.71).








Step 5: Generate reports (Figure 5.72).
